Pipeline Decommissioning
04.58
Oil and gas pipeline decommissioning has been
taking place in the North Sea since the early 1990s, when the Crawford field
pipelines were decommissioned. Since then, pipeline decommissioning has
continued at a modest rate and only when all potential reuse options for the
infrastructure, including new field developments, have been carefully
considered.
Less than 2% of the North Sea pipeline
inventory has been decommissioned, and of the pipelines which have been
decommissioned, 80% are less than 16-in. in diameter. Half of the larger
diameter pipelines (16 in. or greater) decommissioned to date were removed;
these were all infield pipelines less than 1 km (0.6 mi) long. The longest
large diameter trunkline to be decommissioned so far is the 35-km (21.7-mi)
Piper A to Claymore 30-in. export line, which was decommissioned in situ.
Under current regulations, decommissioning of
oil and gas pipelines is considered on a case-by-case basis using the
comparative assessment (CA) process to determine the best option for
decommissioning. The CA process enables the particular diameter, length, and
configuration of individual pipelines to be taken into account when considering
decommissioning options against the criteria of safety, environmental impact,
cost, and technical feasibility.
Health and safety is a dominant factor in any
CA, with the focus aimed at minimizing the long-term risks to other users of
the sea and the short-term risks to those carrying out decommissioning
operations. An integral part of the process is the environmental impact
assessment, which is prepared to support all pipeline decommissioning plans.
Each decommissioning solution needs to be
considered on its individual merits, as pipeline installations vary widely
according to model, location, environment, and maintenance status. It is at the
CA stage, when a number of options are considered, that significant
opportunities exist for supply chain companies to develop innovative
technologies for decommissioning pipelines.
Decommissioning oil and gas installations can
cost operators an average of $4-$10 million in the shallow water Gulf of
Mexico. Thus when the US Department of the Interior Bureau of Ocean Energy
Management, Regulation, and Enforcement (BOEMRE) Gulf of Mexico OCS Region
issued a new decommissioning regulation in September 2010, operators knew
they'd take a hit.
There are 10 steps to the process: Project
Management, Engineering and Planning; Permitting and Regulatory Compliance;
Platform Preparation; Well Plugging and Abandonment; Conductor Removal;
Mobilization and Demobilization of Derrick Barges; Platform Removal; Pipeline
and Power Cable Decommissioning; Materials Disposal; and Site Clearance. Each
step is discussed below.
Project Management
Project management, engineering and planning
for decommissioning an offshore rig usually starts three years before the well
runs dry. The process involves:
- review of contractual obligations
- engineering analysis
- operational planning
- contracting
Due to the limited number of derrick barges,
many operators contract these vessels two to three years in advance. In
addition, much of the decommissioning process requires contractors who
specialize in a specific part of the process. Most operators will contract out
project management, cutting, civil engineering, and diving services.
Permitting And Regulatory Compliance
Obtaining permits to decommission an offshore
rig can take up to three years to complete. Often, operators will contract a
local consulting firm to ensure that all permits are in order prior to
decommissioning. Local consulting firms are familiar with the regulatory
framework of their region.
An Execution Plan is one of the first steps in
the process. Included in this plan is environmental information and field
surveys of the project site. The plan describes a schedule of decommissioning
activities and the equipment and labor required to carry out the operation. An
execution plan is required to secure permits from Federal, State, and local
regulatory agencies. The BOEMRE will also analyze the environmental impact of
the project and recommend ways to eliminate or minimize those impacts.
Federal agencies often involved in
decommissioning projects include BOEMRE, National Marine Fisheries Service, US
Army Corps of Engineers, US Fish and Wildlife Service, National Oceanic and
Atmospheric Administration, US Environmental Protection Agency, US Coast Guard,
and the US Department of Transportation, Office of Pipeline Safety.
Platform Preparation
To prepare a platform for decommissioning,
tanks, processing equipment and piping must be flushed and cleaned and residual
hydrocarbons have to be disposed of; platform equipment has to be removed,
which includes cutting pipe and cables between deck modules, separating the
modules, installing pad eyes to lift the modules; and reinforcing the
structure. Underwater, workers prepare the jacket facilities for removal, which
includes removing marine growth.
Well Plugging And Abandonment
Plugging and abandonment is one of the major
costs of a decommissioning project and can be broken into two phases.
The planning phase of well plugging includes:
- data collection
- preliminary inspection
- selection of abandonment methods
- submittal of an application for BOEMRE
approval
In the GOM, the rig-less method, which was
developed in the 1980s, is primarily used for plugging and abandonment jobs.
The rig-less method uses a load spreader on top of a conductor, which provides
a base to launch tools, equipment and plugs down hole.
Well abandonment involves:
- well entry preparations
- use of a slick line unit
- filling the well with fluid
- removal of down hole equipment
- cleaning out the wellbore
- plugging open-hole and perforated
intervals(s) at the bottom of the well
- plugging casing stubs
- plugging of annular space
- placement of a surface plug
- placement of fluid between plugs
Plugs must be tagged to ensure proper
placement or pressure-tested to verify integrity.
Conductor Removal
According to BOEMRE, all platform components
including conductor casings must be removed to at least 15 ft below the ocean
floor or to a depth approved by the Regional Supervisor based upon the type of
structure or ocean-bottom conditions.
To remove conductor casing, operators can
chose one of three procedures:
- Severing, which requires the use of
explosive, mechanical or abrasive cutting
- Pulling/sectioning, which uses the casing
jacks to raise the conductors that are unscrewed or cut into 40 ft-long
segments.
- Offloading, which utilizes a rental crane
to lay down each conductor casing segment in a platform staging area,
offloading sections to a boat, and offloading at a port. The conductors
are then transported to an onshore disposal site.
Mobilization/Demobilization And
Platform Removal
Mobilization and demobilization of derrick
barges is a key component in platform removal. According to BOEMRE, platforms,
templates and pilings must be removed to at least 15 ft below the mud line.
First, the topsides are taken apart and lifted
onto the derrick barge. Topsides can be removed all in one piece, in groups of
modules, reverse order of installation, or in small pieces.
If removing topsides in one piece, the derrick
barge must have sufficient lifting capacity. This option is best used for small
platforms. Also keep in mind the size and the crane capacity at the offloading
site. If the offloading site can't accommodate the platform in one piece, then
a different removal option is required.
Removing combined modules requires fewer
lifts, thus is a time-saving option. However, the modules must be in the right
position and have a combined weight under the crane and derrick barge capacity.
Dismantling the topsides in reverse order in which they were installed, whether
installed as modules or as individual structural components, is another removal
option and the most common.
Topside can also be cut into small pieces and
removed with platform cranes, temporary deck mounted cranes, or other small
(less expensive) cranes. However, this method takes the most time to complete
the job, so any cost savings incurred using a smaller derrick barge will likely
be offset by the day rate.
Removing the jacket is the second step in the
demolition process and the most costly. First, divers using explosives,
mechanical means, torches or abrasive technology make the bottom cuts on the
piles 15 ft below the mudline. Then the jacket is removed either in small
pieces or as a single lift. A single lift is possible only for small structures
in less than 200 ft of water. Heavy lifting equipment is required for the
jacket removal as well, but a derrick barge is not necessary. Less expensive
support equipment can do the job.
Pipeline And Power Cable
Decommissioning
Pipelines or power cables may be
decommissioned in place if they do not interfere with navigation or commercial
fishing operations or pose an environmental hazard. However, if the BOEMRE
rules that it is a hazard during the technical and environmental review during
the permitting process, it must be removed.
The first step to pipeline decommissioning in
place requires a flushing it with water followed by disconnecting it from the
platform and filling it with seawater. The open end is plugged an buried 3 ft
below the seafloor and covered with concrete.
Materials Disposal And Site Clearance
Platform materials can be refurbished and
reused, scrapped and recycled or disposed of in specified landfills.
To ensure proper site clearance, operators
need to follow a four-step site clearance procedure.
- Pre-decommissioning survey maps
the location and quantity of debris, pipelines, power cables, and natural
marine environments.
- Post decommissioning survey identifies
debris left behind during the removal process and notes any environmental
damage
- ROVs and divers target
are deployed to further identify and remove any debris that could
interfere with other uses of the area.
- Test trawling verifies
that the area is free of any potential obstructions.
Sumber:
http://www.offshore-mag.com/articles/print/volume-74/issue-2/engineering-construction-installation/
http://www.rigzone.com/training/insight.asp?i_id=354
http://www.rigzone.com/training/insight.asp?i_id=354
0 komentar